Kartli Wind Power Plant. Construction in active phase
15 June, 2016
Yesterday our team has visited construction site of Kartli Wind Power Plant. All parties involved in the project were present at on-site meeting, where they have discussed all pending issues and have planned future actions. Construction works are in active phase and project is on schedule.
Our engineers have monitored construction of access road and checked its conformance with technical requirements. All civil works are in progress according to plan and wind turbine components are expected to be delivered to project site from mid August in order to start erection works.